Construction of the foundation slab is progressing on schedule
The common foundation slab of the entire nuclear island of Unit 5, which is approximately three meters thick on average, is being built continuously in several bays. Having regard to the huge size of the area and the complexity of the preparation, the area has been divided into several bays in order to carry out the task efficiently and safely. In these bays, the levelling concrete, which includes waterproofing and grounding mesh is first and foremost prepared, in some areas up to one and a half meters thick. The task of the levelling concrete is to provide a solid, clean and even surface for further work. This is followed by the reinforcement, for which massive, 40 mm diameter reinforcing steel bars are used. The volume is clearly demonstrated by the fact that in the 122 square meters area of the first concrete pouring alone, 133 tons of iron structure increase the load-bearing capacity and durability of the foundation slab. The reinforcement bars extending beyond the structure ensure continuity between the completed foundation slab sections.
After the reinforcement is completed, the fittings to be installed are placed according to the plans, they are formed around them and finally under continuous quality control, special concrete of a quality confirmed by laboratory tests is poured. Since this activity cannot be interrupted, several concrete pumps work in parallel in order to ensure continuous work. The scale is clearly illustrated by the fact that 329 cubic meters of concrete were used to construct the first foundation slab bay. At the end of the process, the hardening and temperature of the concrete are monitored using instruments.
In the excavation pit the different work phases are therefore carried out in parallel in each bay. The levelling concrete of the different areas, the insulation of the levelling concrete, the grounding mesh works, the reinforcement and the concreting of the foundation slabs bay proceed side by side according to the so-called construction organization plan.
Other News
High School Student from Serbia on Rosatom’s Expedition to the North Pole
A student from Serbia has secured a place among the winners of the seventh season of the internation...
Fourth-generation nuclear training: the command-room simulator for the innovative reactor BREST-OD-300 has been put into operation.
At the School and Information Center of the Siberian Chemical Combine in Seversk, a full-scale comma...
The lifespan of the Sizewell B power plant has been extended to 2055: The UK government and EDF have reached a financing agreement.
The British government and energy company EDF have reached a principled agreement on extending the o...
Argentina announces privately-financed SMR plan
In a post on the X social media site the President's Official Spokesman said: "This is the first com...
Comments
No comments yet. Be the first!
Leave a comment