Justification of the concept and preliminary requirements for establishing a Temporary Residential Town (TRT) for about 5,000 people to support the construction of a Small Nuclear Power Plant.
The aim of this Analytical Report is to analyze feasibility, key aspects, and to formulate preliminary technical and organizational requirements for creating a modern Temporary Living Town (TLT), designed for comfortable and safe living of up to approximately 5,000 (five thousand) people of multinational and multicultural workforce.
This Temporary Living Town is intended to provide housing for personnel engaged at all stages of the construction of the ASMM in the Jizzakh Region of the Republic of Uzbekistan.
The ASMM project, according to information as of April–May 2024, envisages the construction of a plant with total capacity of 330 MW (six RITM-200N reactors, each with 55 MW).
Construction contract has been signed between the Agency "Uzatom" and the State Corporation "Rosatom" (Russia), with discussions also underway on a trilateral agreement involving the China National Nuclear Corporation (CNNC) and Shanghai Electric (China).
Startup of the first reactor of the ASMM is planned around 2029, with full design capacity of the ASMM not earlier than 2033.
Latest News
District heating and flexibility: A Finnish company is evaluating options for Helsinki
The Finnish company Helen Ydinvoima Oy has initiated an Environmental Impact Assessment (EIA – Envir...
Cernavoda is back in operation!
Romania is restarting electricity production at its only nuclear power plant at Cernavoda (Cernavodă...
Reactor components completed for El Dabaa 1
Production of the reactor internals and the VVER-1200 reactor head for the unit were produced at Ros...
X-energy selects Fluor for second Xe-100 project
This is the second commercial contract between the two companies for nuclear island engineering and...
Comments
No comments yet. Be the first!
Leave a comment